     2= Moving to Git =
     3
     4Note: **This plan should be considered *alpha*.**
     5
     6== Notes ==
     7
     8 * Target: The 1.53 release is the last Subversion release of the Boost Libraries.
     9 * All dates are targets, not deadlines. We don’t move forward until we are ready.
     10
     11 * During testing:
     12   * The repositories at github.com/boost-lib/* are for testing only and will '''not''' receive a blessing.
     13   * All commits to the Git repository are for testing only and will not be permanent changes. They will be lost!
     14   * Development should continue in Subversion only.
     15
     16== Schedule ==
     17
     18* '''2013-12-15'''
     19   * Rough draft of most documentation for most roles are complete. Help Desk is in place. -- We need a Help Desk link.
     20
     21* '''2013-12-15 – 2013-01-11'''
     22   * Developers beta test Git repository, reporting issues and asking questions on the Help Desk.
     23
     24* '''2013-01-11'''
     25   * Test machines all have Git installed.
     26   * Test script pulling from Git in place.
     27
     28* '''2013-01-11 – 2013-01-18'''
     29   * Test fleet is testing code from Git.
     30
     31* '''2013-01-21 – 2013-01-25'''
     32   * Release managers create Git based “release” that Distro release managers or others may choose to test with.
     33
     34* '''2013-01-28'''
     35   * Subversion is made Read-Only.
     36   * Repositories at github.com/boost/boost-lib/* are recreated and blessed.
     37   * Final pull from Subversion to Git.
     38   * Development continues from Git.