wiki:ModCvtSchedule

Version 4 (modified by Beman Dawes, 10 years ago) ( diff )

Add 1.53 release date

Moving to Git

Note: This plan should be considered *alpha*.

Notes

  • Target: The 1.53 release, scheduled for February 4th, 2013, is the last Subversion release of the Boost Libraries.
  • All dates are targets, not deadlines. We don’t move forward until we are ready.
  • During testing:
    • The repositories at github.com/boost-lib/* are for testing only and will not receive a blessing.
    • All commits to the Git repository are for testing only and will not be permanent changes. They will be lost!
    • Development should continue in Subversion only.

Schedule

  • 2012-12-15
    • Rough draft of most documentation for most roles are complete. Help Desk is in place. -- We need a Help Desk link.
  • 2012-12-15 – 2013-01-11
    • Developers beta test Git repository, reporting issues and asking questions on the Help Desk.
  • 2013-01-11
    • Test machines all have Git installed.
    • Test script pulling from Git in place.
  • 2013-01-11 – 2013-01-18
    • Test fleet is testing code from Git.
  • 2013-01-21 – 2013-01-25
    • Release managers create Git based “release” that Distro release managers or others may choose to test with.
  • 2013-01-28
    • Subversion is made Read-Only.
    • Repositories at github.com/boost/boost-lib/* are recreated and blessed.
    • Final pull from Subversion to Git.
    • Development continues from Git.
Note: See TracWiki for help on using the wiki.